PROJECT PROGRESS REPORT-For the Period Ending: January 11, 2008
PROGRESS DURING QUARTER
Offsite remediation-
Ongoing tracer study at B4 area. Tracer detected in several downgradient wells
Database management
QW data into their ITEMS/ERPIMS database-Need to evaluate "bad QW" data and link to specific site in header file. No Progress
Geophysical database-Need to add flow meter, ATV, OTV data and to generate layouts. No Progress.
Aquifer test data-Need to put approved slug test data into GWSI. No Progress.
WL data-QA/QC and entry of data for 8 wells. Data is being prepared for download to ADAPs.
Began development of project web page. This will serve as a repository for geophysical, qw, and water-level data, and for published reports.
Letter report to ASC describing all databases and data availability-Pending completion of other tasks.
Monitoring well construction
All retrofits completed with the exception of RW203-On hold until tracer tests completed.
B4 Remediation evaluation monitoring
-Reevaluated network and frequency of sampling. Met with Amy Potter to discuss in December. See attached table.
B4 Water level network - Processing and QA/QC of data is still lagging.
REPORTS AND PRESENTATIONS
See attached table
MEETINGS
12/17/07 JSC met with Amy Potter regarding scope of USGS water-quality monitoring activities. Network has been revised (see above).
OTHER
PLANS FOR NEXT QUARTER
Offsite remediation
-Continue to monitor tracers near South Cobb Drive remediation area.
Database management
QW data into their ITEMS/ERPIMS database-Complete this quarter. Need to evaluate "bad QW" data and link to specific site in header file.
Geophysical database-Add flow meter, ATV, OTV data; prepare for web layout
Aquifer test data archive-Ensure consistent with Gonthier report, add slug tests to GWSI
WL data-Complete QA/QC of all data for 8-site network.
Project WEB page--Continue development. Incorporate geophysical log archive, water-level and qw data.
B4 Remediation evaluation monitoring
- Collect next series of samples in March
B4 Water level network
- Service recorder network in January.
Reports:
Continue progress on reports (see table)
Other:
Partnering meeting, February 7 (tentative)
Need to schedule meeting with new Air Force coordinator, John Doepker (Feb 6?)